Launched early January, the studies d’execution of the Oise-au-Vert project opened the way to a new structuring phase: earthworks. This site, located in the department of l’Oise (60), is the second developed, financed and built by SWING Biomethane in France. With a target production of 35 GWh of biomethane per year, Oise-au-Vert embodies our integrated approach to biomethane project development: rigorous upstream studies, co-development with local stakeholders and operational mastery of all construction phases.
Launched early January, the studies d’execution of the Oise-au-Vert project opened the way to a new structuring phase: earthworks. This site, located in the department of l’Oise (60), is the second developed, financed and built by SWING Biomethane in France. With a target production of 35 GWh of biomethane per year, Oise-au-Vert embodies our integrated approach to biomethane project development: rigorous upstream studies, co-development with local stakeholders and operational mastery of all construction phases.
Where is the Oise-au-Vert site today?
Since the effective start of the works, the teams of SWING Biomethane and partner companies have advanced significantly on the earthworks phase. This step, often perceived as purely technical, is in reality the foundation of the entire life of the future industrial site. It prepares l’reception of digesters, storage pits, buried networks, technical platforms and the regulatory retention zone required by the ICPE decree applicable to methanisation units.
The construction site follows a tight but controlled schedule, reflecting the preparatory work carried out during the execution studies. The soil studies and topographic surveys conducted upstream provide the work teams today with a clear view of the site constraints: soil bearing capacity, levels to be adjusted, water pathways, zones to be purged. This anticipation avoids unpleasant surprises and secures the commissioning schedule.
Excavation: much more than ’un « shovel strike »
Excavation d’une methanisation unit is not limited to leveling a terrain. It is a precision work that determines durability and performance of the structures for several decades. On the Oise-au-Vert site, the teams intervene on several dimensions simultaneously.
Stabilize the terrain for decades d’exploitation
The digesters d’une biomethane plant are massive structures, capable of containing several thousand cubic meters of fermenting material. The ground that supports them must be perfectly stable to avoid any differential settlement that could crack the tanks. In Oise-au-Vert, the earthworks incorporate continuous bearing verification, with purges and material substitutions when necessary.
Manage the levels and water flows d’eau
A well‑graded construction site, it’s also a site where the ’water flows in a controlled manner. Slopes are calculated to the centimeter to direct rainwater to collection points, avoid stagnation around technical structures and ensure the proper functioning of the retention area. The latter, mandatory on any classified installation, allows effluents to be contained in case of d’incident and ensures the environmental compliance of the site with the DREAL.
Prepare the foundations and future circulations
Excavation also prepares the foundation zones, the delivery areas for agricultural inputs, the circulation routes of the d’exploitation and the fire access points. Every square meter of the site is designed to optimise future flows: arrival of organic materials, removal of digestate, maintenance of equipment. This spatial organisation, decided well in advance, determines the daily productivity of the l’unité once in operation.
Why do upstream studies change everything on a biomethane site?
At SWING Biomethane, the success d’an excavation is determined well before the first excavators. From the development phase, we commission comprehensive geotechnical and topographic studies. This data directly feeds the sizing of the site and the accuracy of budget estimates.
This approach allows us to identify upstream the technical constraints that could increase cost or schedule: surfacing groundwater table, highly variable clayey soil, presence of existing networks, landscape constraints. By anticipating them, we secure the project's financial model and give our co-development partners solid visibility on the project's trajectory. It is a fundamental principle of our method: mastering the project in construction means having properly prepared it in development.
Oise-au-Vert in a few figures
- Location: department of Oise (60), Hauts-de-France
- Target production: 35 GWh/year of biomethane injected into the GRDF network
- Equivalent consumption: approximately 3,000 households heated with renewable gas
- Current stage: earthworks and preparation of the platforms
- Model: co-development with local agricultural actors
And after the earthworks?
Once the earthworks phase is completed, the site will enter its civil engineering phase: casting of the foundations, construction of the digesters, pre‑treatment and storage structures. Then the equipment package (purifier, torch, injection station) will follow, and finally the industrial commissioning phase. The SWING Biomethane team supervises each of these steps with partner EPC companies, relying on the technical expertise its leaders have acquired from more than 25 installations in Europe.
Oise-au-Vert concretely illustrates our value proposition: develop, finance, build and operate biomethane units in sustainable partnership with territories. The monitoring of the site will be l’object of upcoming publications, in order to share with our agricultural, industrial and financial partners the progress of this emblematic project.